1. 单选题
20 秒

What is the PI System Demo a part of? 

Iteration planning

I&A

Team retrospective

Daily Stand-up

2. 单选题
20 秒

What is used to identify the biggest root cause? 

Brainstorming

5 Whys

Pareto analysis

Retrospective

3. 单选题
30 秒

About Team PI performance report, which statement is FALSE?

Business Value is provided by the Business Owners

 Planned total does not include uncommitted objectives

Actual total includes uncommitted objectives

A team can NOT achieve greater than 100% 

4. 单选题
30 秒

What's the first step of the problem-solving workshop?

Apply root-cause analysis and 5 whys

Brainstorm solutions 

Agree on the problem to solve

 Identify improvement backlog items

5. 单选题
30 秒

About PI system demo, which statement is TRUE?

It's same as system demo

Only Agile teams in the ART will join in

It's happened at the end of the PI

It demos new features for the most recent iteration delivered by the ART