成品80180951在APO中的Procurement Type为?
E
F
X
P
北京工厂 纸箱 85032984 的需求类型为?
Dependent Demand
Forecast
Distribution Demand
Independent Demand
系统运行完JOB后,没有经过人为修改。发现某一个Bulk订单的需求时间为"2023-12-01",该订单预计放行时间为"2024-03-01",则最有可能出现的Alert为?
Product too early (Fixed pegging)
Product too early (Dynamic pegging)
Receipt due date/time violated (Dynamic pegging)
Receipt due date/time violated (Fixed pegging)
Product too late (Fixed pegging)
Start date in the past
PP/DS中的"PP"是指?
Procurement Plan
Production Plan
Personal Plan
Projected Plan
假设当前日期为2023-12-01,手动删除某一成品的全部Planned Order后,立即运行MRP并查看结果,发现某一个Planned Order开始时间为2023-12-12,则最有可能出现的Alert为?
Product too late (dynamic pegging)
Opening date in the past
Order not scheduled
Product too early (dynamic pegging)
假设某一生产订单计划批量为10000 PCE,生产至5000 PCE时,因故需要结束“收货”并关闭订单并进行财务结算,该订单剩余数量不再继续生产,则必须进行的"收货"操作为?
PCNF
CNF
PDLV
DLV
下图最有可能出现在哪个Alert Profile里?
Overall Alert Profile
Application-Specific Alert Profile
APO: Production Planning / Detailed Sch. Profile
Location Products Profile
某位计划员在使用Alert时,想将图中第一列的"Location", 调整至第三列显示,则需要调整的内容为?
Layout
Alert Profile
Variant
Personal Setting